Blended Rate Cost

Blended Rate Cost

Blended Rates will produce simplified cost calculations by applying a single unit price to the Meter data. The prices are associated to a Path in the Tree and the cost calculations cascade through to the Meters by fuel and measurement units.  Useful if the Meter does not have a Contract associated with it..

In Analysis, Blended Costs can be selected as an alternative to the Cost or Revenue Contract outputs. Blended Costs will only appear as selectable outputs for certain Analysis types:

Viewing Blended Rates

  • Open: Financial > CONTRACT > Blended Rate Cost

image-20240131-154405.png

Searching Options

  • Path - click Select to choose the Path

  • Fuel - choose from the dropdown

  • Unit - choose from the dropdown

  • Currency - choose from the dropdown

Adding Blended Rates

Tip - you must have a Path selected to add Blended Rates

  • Click Add to open the Blended Rates Page

image-20240131-154752.png
  • Path - the Path will be populated with the Path chosen in the previous Page

  • Fuel - choose from the dropdown

  • Unit - choose from the dropdown (the list of options only shows the units found for the Fuel selected above

  • Currency - defaults to British Pounds (GBP)

image-20240131-155106.png

Search Results section

  • Effective From - choose the effective from date

  • Value - add the Value. For example enter 0.45 for 45p or 1.50 for £1.50

  • Click Insert

image-20240131-155341.png

Adding Additional Rates manually

  • Click Add to open the Blended Rates Page

  • Search for the Path, Fuel, Unit and Currency

  • Click Add

  • Effective From - is a date entered to establish the start date of the latest value. The preceding values will end at 23:59 of the previous date. A value remains effective for blended cost calculation until a following value is inserted. 

  • Value - add the Value. For example enter 0.45 for 45p or 1.50 for £1.50

  • Click Insert

The previous Rate is automatically ended and both Rates show in the Search Results

image-20240131-155837.png

Editing Blended Rates

  • Click Edit

image-20240815-082538.png
  • Make any changes and click Update to return to the Blended Rates Page

Deleting Blended Rates

  • Click Delete

image-20240815-082509.png

Exporting Blended Rates

  • Click Export All to download a list of the search results displayed as a CSV file

image-20240131-160556.png

Creating Projected Rates

Create Projected Rates generates a sequence of annual, incremental values.

  • Click Create Projected Rates to open the Projected Rates popup

image-20240131-160725.png
  • Difference % - enter the % increment per year

  • Baseline From Date - enter the Baseline From Date (defaults to the date of the first Blended Rate

  • Years - enter the number of yearly records to create

  • Click Project to return to the Blended Rates Page, showing the Projected Rates

image-20240131-161013.png

Importing Blended Rates

Blended Rates can be imported from a CSV file. The imported rates will apply to the combination of items searched: Path, Fuel, Unit and Currency.

Although there is not a sample File, export the existing Blended Rates and use this as an example of the format.

Once you have created the File:

  • Search to the required Path, Fuel, Unit and Currency

  • Click Select and select your File

  • Click Import

image-20240325-132451.png

The screen updates to show the success of the File.

image-20240325-132533.png

Using Blended Rates

Once Blended Rates have been added, they can be used in the following Analysis Reports:

Running Reports

  • Run the Report as per the above links and choose Blended Rates from the Output Type

image-20240815-082724.png

The Report will show the Cost using the appropriate Blended Rates.

image-20240325-133356.png

The Consumption for the September period is 51397.60 kWh. Running the Report on Blended Rates will multiply the Consumption by the Blended Rate relevant to the time period, ie 0.55 (55p), which equals £28268.70.